Debris Removal update January 30, 2017

Below is the 1/30/2017 summary of Beaufort County debris removal and hazardous tree removal operations:

Vegetative and C&D Debris Removal Operation:

  • Total:  143 loads / 7,604  Cubic Yards (*Including 98 loads / 5054.60 CYD from Daufuskie Island)
  • Vegetative/Wood – 7,535 CY (*Including 5054.60 CYD from Daufuskie Island)
  • Construction & Demolition 46 CY (*Including 0 CYD from Daufuskie Island)
  • Uprooted Stumps – 23 CY (*Including 0 CYD from Daufuskie Island)

Haul-Out Operation:

  • Total:  36 loads / 3616.05 Cubic Yards (*Including 0 loads / 0 CYD from Daufuskie Island)

LHS Hazardous Tree Removal Operation:

  • 83 total tickets issued (*Including 0 total from Daufuskie Island)
  • Hazardous Limbs – 79 (*Including 0 from Daufuskie Island)
  • Hazardous Trees – 4 (*Including 0 from Daufuskie Island)

*Please note – Stump totals on the LHS Status Report are indicative of completely uprooted stumps collected on a cubic yardage basis and not stump extractions. There were 3 completely uprooted stumps (23 CY) collected today.

Attached are the PDF reports for Unit Rate and Load tickets in order to document field operation and daily/cumulative totals. Please note all figures are pending final reconciliation with the contractor.

2017-01-30_BeaufortCounty_DebrisRemovalStatus

2017-01-30_BeaufortCounty_LHSStatus

2017-01-30_BeaufortCounty_ProjectHauloutSummary